Home » Products » Asphalt Mixing Plant » Key points of the power-on trial operation of asphalt mixing plant

Key points of the power-on trial operation of asphalt mixing plant

Asphalt mixing plant is one of the main equipment for producing asphalt concrete. It can mix asphalt, gravel, cement and other materials together in a certain proportion to obtain the products required for highway construction. In order to ensure its operating effect, the asphalt mixing plant also needs to be powered on for trial operation before it is officially put into work.
The first step in commissioning is to run a single motor and check whether the current, steering, insulation and mechanical transmission parts are operating normally. After confirming that each motor and mechanical transmission parts are operating correctly, conduct a joint trial run. During the entire process, it is necessary to conduct patrol inspections of key parts. If any abnormal noise is found, the cause should be identified and eliminated in a timely manner.

Rated 4.6/5 based on 575 customer reviews
Share:
Content

Asphalt mixing plant is one of the main equipment for producing asphalt concrete. It can mix asphalt, gravel, cement and other materials together in a certain proportion to obtain the products required for highway construction. In order to ensure its operating effect, the asphalt mixing plant also needs to be powered on for trial operation before it is officially put into work.
The first step in commissioning is to run a single motor and check whether the current, steering, insulation and mechanical transmission parts are operating normally. After confirming that each motor and mechanical transmission parts are operating correctly, conduct a joint trial run. During the entire process, it is necessary to conduct patrol inspections of key parts. If any abnormal noise is found, the cause should be identified and eliminated in a timely manner.
After turning on the power, turn on the air compressor to make the air pressure reach the rated pressure value. During this process, you can clearly observe whether there is air leakage in the control valve, pipeline, cylinder and other components. Then connect the oil supply and return devices, oil supply and return pipelines, etc., and ensure that they do not leak. At the same time, use anti-rust components or take anti-rust measures.
Since the asphalt mixing plant contains many mechanical components, a complete set of commissioning operations requires consideration of all aspects, such as the hydraulic department, conveying mechanism, dust removal system, etc., and none of them can be left out.

Inquiry


    More Asphalt Processing

    The drying drum of the asphalt mixing plant should pay attention to daily inspection, correct operation and reasonable maintenance, so as to extend its service life and reduce the cost of engineering use.
    1. Pay attention to daily inspection. Before the asphalt mixing plant officially works, the drying drum needs to be tested and inspected to see whether each pipeline is reliably connected, whether the lubrication of the whole machine is feasible, whether the motor can be started, whether the functions of each pressure valve are stable, whether the instrument is normal, etc.
    2. Correct operation of the mixing station. At the beginning of the asphalt mixing plant, manual operation can only switch to automatic control after reaching the specified production capacity and discharge temperature. The aggregate should be dry and have a standard mode so that it can maintain a constant temperature when flowing through the drying drum. When the entire aggregate is sent to dry, the moisture content will change. At this time, the burner should be used frequently to compensate for the change in moisture. During the rolling stone processing, the amount of water directly formed is basically unchanged, the amount of combustion accumulation increases, and the amount of water in the deposited accumulation material may change.
    3. Reasonable maintenance of the asphalt mixing plant. Aggregates should be deactivated when the asphalt mixing plant is not in operation. After work every day, the equipment should be operated to discharge the aggregate into the dryer. When the material in the hopper leaves the combustion chamber, the combustion chamber should be closed and allowed to idle for about 30 minutes to cool down, so as to reduce its impact or make the machine run in a straight line. Install the drying cylinder fixing ring on all rollers synchronously.

    Asphalt mixing stations, also known as asphalt concrete mixing stations, can produce asphalt mixtures, modified asphalt mixtures, and colored asphalt mixtures, which fully meet the needs of building highways, grade roads, municipal roads, airports, ports, etc. Changmeng Electric Power introduces the safety operating procedures of asphalt mixing plants below:
    1. During the operation of the mixing equipment, in addition to ensuring that the equipment is in good condition, it should also be equipped with a mineral moisture content detector and a finished material tester, and the relevant data should be frequently tested for the operator to adjust the operation in time to keep the equipment in good condition.
    2. In addition to affecting production capacity, the moisture content of mineral materials is also the main factor determining fuel consumption. Additional material sheds should be added.
    3. Before operation, all working parts and devices of the mixing equipment should be fully checked to see if they are intact and normal. If there are any problems, they must be properly handled before operation, and it is forbidden to operate with illness.
    4. The operation must be carried out strictly in accordance with the procedures and precautions specified in the instruction manual. After normal ignition, the dust collector should be monitored to ensure that the drying drum burns under negative pressure; after production starts, the hot material elevator and agitator should be monitored to see if they are working normally to coordinate the operation of other parts.

    The materials used in asphalt mixtures contain a lot of dust. When the equipment is operating, if the dust enters the atmosphere, it will cause pollution. Therefore, dust removal equipment must be installed, and now bag dust removal is the main method. Safety is a common sense issue. There are well-established standard safety rules.
    Do not clean, oil or adjust any mechanical equipment that is not specifically explained during operation; turn off the power and lock it before inspection or repair activities to prepare for accidents. Because each situation has its own particularity. Therefore, be vigilant about safety damage issues, incorrect operation issues and other deficiencies. All of them may lead to accidents, personal injuries, reduced production efficiency, and more importantly, loss of life. Careful and early prevention is the best way to avoid accidents.
    Careful and correct maintenance can make the equipment work more efficiently and control it within a certain level of pollution; the maintenance of each component should be carried out according to its operating standards; maintenance plans and safe operation procedures should be formulated according to the inspection and repair conditions that must be carried out.
    Take out a work log to record all inspection and repair conditions, list the analysis of each inspection of each component and the description of the repair content or the date of the repair; the second step is to give the inspection cycle for each component, which should be determined according to the service life and wear condition of each component.