At present, most asphalt mixing plants have different degrees of energy loss in use, and these losses have brought us serious waste. How to reduce energy consumption in these aspects and achieve efficient production?
First of all, we must first summarize which aspects have energy loss, and then we can find reasonable solutions based on these problems. Through research, it is found that there are four problems in the use of asphalt mixing plants and the production of asphalt mixtures. The content and measures are as follows:
The first aspect is the management of the pile. We can reduce the energy consumption of the asphalt mixing plant through 3 specific methods: 1. Appropriately reduce the stacking height of the pile; 2. Build an inclined pile site with a good drainage structure; 3. Build a waterproof canopy.