Home » Application » Road Maintenance » The whole process of slurry sealing truck construction

The whole process of slurry sealing truck construction

1. Preparation before construction
2. Mix
3. Paving
4. Leveling
5. Shutdown
6. Overlap
7. Crush

Rated 4.7/5 based on 221 customer reviews
Share:
Content

1. Preparation before construction
Before the construction of the slurry sealing truck, the penetration layer should be checked for soil contamination, and the contaminated parts should be washed in advance and emulsified asphalt should be sprayed.
2. Mix
The mixture must be mixed evenly without clumping, clumping or whitening. When such a situation occurs, paving should be stopped, the reasons should be checked from the aspects of mineral material gradation, oil-stone ratio, mixing speed, time, etc., and adjustments should be made in a timely manner.
3. Paving
The rubber scrapers around the paving trough must be installed accurately and firmly to ensure that the mixture in the trough is spread as required and no leakage occurs. The mixed slurry mixture flows into the paver box. When the volume of the mixture reaches 2/3 of the volume of the paver box and is filled with material in the road width direction, the paver is started to advance at a constant speed of 1.5 to 3km/h. When paving, the slurry paving amount and mixing amount should be kept basically the same, and the volume of the slurry mixture in the paver box should be about 1/2 of the paver box.
4. Leveling
Immediately after the slurry mixture is spread, manual leveling is performed using a rubber rake. The focus of leveling is on areas that are too thick, too thin or uneven. Any leaks or insufficient slurry should be repaired immediately. When leveling, special attention should be paid to longitudinal scratches caused by oversized aggregates, which should be removed and filled as soon as possible.
5. Shutdown
When any kind of material in the paver is used up, immediately turn off the control switch of all material transportation, let the mixture in the mixing drum be mixed and sent to the paving box. After paving is completed, the paver will stop moving forward.
6. Overlap
The overlap width of two longitudinal seams should not exceed 80mm, and the transverse seams should be made into butt joints. There should be no accumulation of residual material or lack of material at the joints, and the unevenness should not be greater than 6mm.
7. Crush
After the slurry seal layer is laid for initial setting (usually after 30 minutes), it is rolled twice with a tire roller. If defects such as clumps or looseness are found, they should be removed and resurfaced.
The thickness of the paving should be measured at any time on site. If the thickness is found to be inappropriate, the operator should be promptly reminded to adjust the paving thickness.
Traffic control should be implemented after the slurry seal is laid, and traffic can only be opened after it is dried and formed.

Inquiry


    More Road Maintenance

    Asphalt spreader is used to spread the penetration oil, waterproof layer and bonding layer of the bottom layer of asphalt pavement of high-grade highway. It can also be used for the construction of county and township highway oil roads with layered paving technology. It consists of a car chassis, an asphalt tank, an asphalt pumping and spraying system, a thermal oil heating system, a hydraulic system, a combustion system, a control system, a pneumatic system, and an operating platform.
    Knowing how to properly operate and maintain the asphalt spreader can not only extend the service life of the equipment, but also enable the construction project to proceed smoothly. So what problems should the asphalt spreader pay attention to when working? The technicians of Gaoyuan Road Construction Machinery Equipment Co., Ltd. give you tips:
    1). Before use, please check whether the position of each valve is accurate and make preparations before work. After starting the motor of the asphalt spreader, check the four thermal oil valves and the pressure gauge. After everything is normal, start the engine and the power take-off starts to work. Test the asphalt pump and circulate for 5 minutes. If the pump head shell is hot, slowly close the thermal oil pump valve. If the heating is insufficient, the pump will not turn or make noise. In this case, the valve needs to be opened to continue heating the asphalt pump until it can operate normally. During the working process, the asphalt liquid must be kept at a working temperature of 160~180℃, and it cannot be filled too full (pay attention to the liquid level pointer during the injection of asphalt liquid, and check the tank mouth at any time). After the asphalt liquid is injected, the filling port must be closed tightly to prevent the asphalt liquid from overflowing during transportation.
    2). During use, asphalt may not be pumped in. At this time, it is necessary to check whether the interface of the asphalt suction pipe is leaking. When the asphalt pump and pipeline are blocked by solidified asphalt, a blowtorch can be used for baking, and the pump must not be forced to turn. When baking, care should be taken to avoid directly baking the ball valve and rubber parts.
    3). When spraying asphalt, the car should be driven at a low speed. Do not step on the accelerator hard, otherwise it may cause damage to the clutch, asphalt pump and other components. If 6m wide asphalt is spread, pay attention to obstacles on both sides at any time to prevent collision with the spreading pipe. At the same time, the asphalt should be kept in a large circulation state until the spreading work is completed. After the work is completed every day, if there is any remaining asphalt, it must be returned to the asphalt pool, otherwise it will solidify in the tank and cannot work next time.
    4). In addition, the emulsifier must also pay attention to daily maintenance:
    1. The emulsifier and delivery pump and other motors, agitators, and valves should be maintained daily.
    2. The emulsifier should be cleaned after work every day.
    3. The speed regulating pump used to control the flow should be regularly tested for accuracy, and adjusted and maintained in time. The asphalt emulsifier should regularly check the matching clearance between its stator and rotor. When the minimum clearance specified by the machine cannot be reached, the stator and rotor should be replaced.
    4. If the equipment is out of use for a long time, the liquid in the tank and pipeline should be emptied (the emulsifier aqueous solution should not be stored for a long time), the hole covers should be tightly closed, kept clean, and the running parts should be filled with lubricating oil. When it is used for the first time or when it is used again after a long period of inactivity, the rust in the tank should be removed, and the water filter should be cleaned regularly.
    5. Regularly check whether the terminal in the electric control cabinet is loose, whether the wires are worn during shipment, and remove dust to avoid damage to the machine parts. The frequency converter is a precision instrument. Please refer to the instruction manual for specific use and maintenance.
    6. There is a heat transfer oil coil in the emulsifier water solution heating stirring tank. When injecting cold water into the water tank, the heat transfer oil switch should be turned off first, and then the switch should be turned on to heat after adding the required amount of water. Pouring cold water directly into the high-temperature heat transfer oil pipeline can easily cause the weld to crack.

    Water is one of the raw materials of the modified asphalt storage tank, and it is distributed in various components of the modified asphalt storage tank equipment. According to the components where water is distributed, the anti-cold measures are explained one by one. The water tank of the modified asphalt storage tank, the water inside the water tank is released through the filter valve. Some instruments of the modified asphalt storage tank do not have a filter valve to save the cost of the equipment. The modified asphalt storage tank can only be drained by loosening the flange bolts at the bottom. The water pump of the modified asphalt storage tank mentioned here includes a hot water pump and a circulating water pump. This type of water pump for the modified asphalt storage tank generally uses a pipeline centrifugal pump. There is a sewage outlet at the bottom of the pipeline centrifugal pump. The modified asphalt storage tank pays attention to the sewage treatment of the sewage outlet at the bottom of the pump. The modified asphalt storage tank emulsion tank generally uses a cone bottom. However, in order to better process the modified asphalt storage tank coefficient, the inlet and outlet are usually not placed at the bottom of the modified asphalt storage tank. Emulsion (mostly water) will remain at the bottom of the tank, and this part of the residual liquid in the modified asphalt storage tank must be discharged through the filter valve at the bottom. Emulsion pump for modified asphalt storage tank There are basically two types of emulsion pumps for modified asphalt storage tank equipment on the market, gear pumps or centrifugal water pumps. Gear pumps can only discharge the liquid inside the pump through the connection flange of the pipeline. The centrifugal water pump for modified asphalt storage tanks uses its own sewage outlet for sewage treatment. The first four items of modified asphalt storage tanks with basic knowledge are basically discharged, and the modified asphalt storage tanks will focus on the latter types. Modified asphalt storage tank colloid mill There will also be residual emulsion or water inside the modified asphalt storage tank colloid mill. The gap between the stator and rotor of the colloid mill is within 1mm. If there is a little residual water in the modified asphalt storage tank, it will cause the accident of frozen modified asphalt storage tank. The residue in the colloid mill can be treated by loosening the connection bolts of the finished product pipeline.

    From the current point of view, road construction machinery has bottomed out and asphalt meltering equipment has risen rapidly. In recent years, highway construction and maintenance departments have a strong awareness of using asphalt mixing equipment, especially in developed coastal areas such as Beijing, Shanghai, Jiangsu, Zhejiang, etc. In addition, these regions have a fast economic growth rate, relatively developed industry, and strong comprehensive economic strength. Therefore, the consumption of asphalt mixing equipments in these regions has always been at the forefront of the country. With the rapid development of highway construction and the increase in demand for asphalt, barreled asphalt has been widely used for its convenient transportation and easy storage. In particular, most of the high-performance imported asphalt used in high-grade highways is in barrel form, which requires an asphalt meltering equipment with fast melting speed, clean de-barreling, and can prevent asphalt aging. my country’s highway construction has achieved remarkable results, among which mechanized production has contributed greatly. Different types of asphalt mixers and bitumen meltering equipment are selected for the characteristics of large highway pavement construction and tight construction period. With the rapid development of my country’s economy, the further extension of expressways, and the large-scale development of western construction, the central and western regions have become new investment hotspots. While paying attention to the market in the developed eastern regions, domestic road construction machinery manufacturers have also increased their efforts to develop the central and western markets, creating new highlights for the domestic asphalt mixing plants consumer market. In summary, my country’s asphalt mixing plant sales market has begun to move westward with the westward movement of investment hotspots. As the market center of gravity gradually shifts westward, the market in the western region is gradually heating up. The self-heating integrated structure, hot air barrel melting and bitumen barrel flipping technology in the asphalt barrel removal equipment are our company’s self-heating integrated structure. The thermal oil furnace used in the old equipment is perfectly integrated with the asphalt barrel removal equipment body, which reduces the volume of the entire set of equipment, greatly reduces equipment investment, saves equipment space and transfer transportation costs.