Installation and use guidelines for the discharge system of an asphalt mixing plant
After the asphalt is mixed in the asphalt mixing plant, it will be discharged through a special discharge system, which is also the last link in the asphalt mixing work. Even so, there are things that need attention.
For the discharge system of the asphalt mixing plant, first of all, ensure that it is installed stably; secondly, after each mixing, the residual amount of the discharged material must be controlled to about 5% of the discharge capacity, which is also to ensure the mixing efficiency. At the same time, cleaning the inside of the mixer will help extend the service life of the equipment.
After the asphalt is discharged from the mixing plant, the door needs to be closed reliably, and check whether there is residual slurry blocking or leakage and other undesirable phenomena. If there is, it should be taken seriously and inspected and repaired in time.